LIVE DEMO NEC4 ECC Option C
P6Pulse.Com Demonstration Project
Reporting period
Changes compared with previous updateActual % complete
29.6%
Planned 34.7% · +8.7% in period
SPI
0.85
Earned ÷ planned (duration weighted)
Forecast completion
18 Oct 2025
Baseline 23 Sept 2025
Variance vs baseline
+25.2d
+15.4d movement this period
CPLI
0.87
Critical path length index
BEI
0.86
Baseline execution index
Critical activities
16
16 with negative float
Worst total float
-25.2d
Avg float erosion
-8.1d
vs previous update
Starts in period
3/5
Actual / baseline planned
Finishes in period
2/4
Actual / baseline planned
DCMA score
5/14
Checks passed
Contract adjustments · not in baseline
Early warnings & compensation events
CEs excludedEWs excluded
Completion Date
23 Sept 2025
CEs not applied
Forecast completion
18 Oct 2025
EWs not applied
Adjusted variance
+25.2d
same as baseline variance
CE cost confirmed
£48,500
£36,500 pending
Live EW exposure
£8,000
2 live · 15d
Data date 01 Apr 2025
Overall progress S-curve
- Actual
- Actual in month
- Forecast
- Planned (baseline)
- Planned in month
Incomplete activities (days)
Total float distribution
Baseline vs forecast
Key dates & milestones
| ID | Milestone | Status | Baseline | Previous | Forecast | Var (d) | Moved (d) | TF |
|---|---|---|---|---|---|---|---|---|
| A1000 | Contract Starting Date | Complete | 06 Jan 2025 | 06 Jan 2025 | 06 Jan 2025 | 0.0 | 0.0 | — |
| A1010 | Access Date - Site Possession | Complete | 20 Jan 2025 | 20 Jan 2025 | 20 Jan 2025 | 0.0 | 0.0 | — |
| A1900 | Sectional Completion - Bridge | Not started | 30 Jun 2025 | 10 Jul 2025 | 14 Jul 2025 | +14.0 | +4.0 | 96.2 |
| A1990 | Completion Date | Not started | 23 Sept 2025 | 03 Oct 2025 | 18 Oct 2025 | +25.2 | +15.4 | -25.2 |
Lowest total float
Critical & near-critical
| ID | Activity | Start | Finish | TF (d) |
|---|---|---|---|---|
| W1010 | Bulk Earthworks Cut | 01 Apr 2025 | 16 May 2025 | -25.2 |
| W1030 | Carrier Drainage Installation | 16 May 2025 | 15 Jun 2025 | -25.2 |
| W1050 | Filter Drains & Gullies | 15 Jun 2025 | 05 Jul 2025 | -25.2 |
| P1000 | Sub-base & Capping Layer | 10 Jul 2025 | 09 Aug 2025 | -25.2 |
| P1010 | Kerbs & Footways | 20 Jul 2025 | 14 Aug 2025 | -25.2 |
| U1040 | Traffic Signals Installation | 14 Aug 2025 | 13 Sept 2025 | -25.2 |
| C1000 | Signals Commissioning | 13 Sept 2025 | 23 Sept 2025 | -25.2 |
| C1020 | Road Safety Audit Stage 3 | 23 Sept 2025 | 03 Oct 2025 | -25.2 |
| C1030 | As-built Records & H&S File | 28 Sept 2025 | 18 Oct 2025 | -25.2 |
| A1990 | Completion Date | 18 Oct 2025 | 18 Oct 2025 | -25.2 |
| P1020 | Binder Course | 09 Aug 2025 | 24 Aug 2025 | -22.2 |
| P1030 | Surface Course | 24 Aug 2025 | 03 Sept 2025 | -22.2 |
| P1040 | Road Markings & Studs | 03 Sept 2025 | 10 Sept 2025 | -22.2 |
| P1052 | Vehicle Restraint System | 27 Aug 2025 | 08 Sept 2025 | -10.2 |
| P1051 | Permanent Signage | 27 Aug 2025 | 06 Sept 2025 | -8.2 |
| U1020 | Street Lighting Ducting | 05 Jul 2025 | 25 Jul 2025 | -5.2 |
| W1020 | Embankment Fill & Compaction | 11 Apr 2025 | 21 May 2025 | 0.25 |
| U1030 | Street Lighting Columns & Cabling | 25 Jul 2025 | 19 Aug 2025 | 2.8 |
| C1010 | Lighting Energisation | 19 Aug 2025 | 26 Aug 2025 | 2.8 |
| D1030 | Technical Approval (AIP) | 12 Mar 2025 | 05 Apr 2025 | 4 |
| S1000 | Piling - Abutments | 05 Apr 2025 | 25 Apr 2025 | 4 |
| S1010 | Pile Caps, Abutments & Wingwalls | 25 Apr 2025 | 25 May 2025 | 4 |
| S1020 | Precast Beam Installation | 25 May 2025 | 30 May 2025 | 4 |
| S1030 | Bridge Deck Slab | 30 May 2025 | 29 Jun 2025 | 4 |
| S1040 | Parapets & Waterproofing | 29 Jun 2025 | 14 Jul 2025 | 4 |