LIVE DEMO NEC4 ECC Option C
P6Pulse.Com Demonstration Project
CE time (confirmed)
12.0d
Excluded from totals
CE cost (confirmed)
£48,500
1 accepted / implemented
CE pending
£36,500
2 open · 15.0d
Live early warnings
2
15.0d potential · excluded from totals
EW cost exposure
£8,000
Excluded from totals
| Ref | Title | Status | Notified | Clause | Time (d) | Cost | |
|---|---|---|---|---|---|---|---|
| CE-001 | Additional drainage outfall requested by the Client | Accepted | 10 Feb 2025 | 60.1(1) | 12 | £48,500 | |
| CE-002 | Statutory undertaker diversion delayed | Quotation Submitted | 10 Feb 2025 | 60.1(12) | 9 | £21,000 | |
| CE-003 | Unforeseen soft ground at north embankment | Notified | 10 Feb 2025 | 60.1(12) | 6 | £15,500 |