You're viewing the live demo: a real sample project, read-only. Click through the reports, registers, photos and downloads.

Start your own project
LIVE DEMO NEC4 ECC Option C

P6Pulse.Com Demonstration Project

Reporting period
Changes compared with previous update

Actual % complete

29.6%
Planned 34.7% · +8.7% in period

SPI

0.85
Earned ÷ planned (duration weighted)

Forecast completion

18 Oct 2025
Baseline 23 Sept 2025

Variance vs baseline

+25.2d
+15.4d movement this period

CPLI

0.87
Critical path length index

BEI

0.86
Baseline execution index

Critical activities

16
16 with negative float

Worst total float

-25.2d

Avg float erosion

-8.1d
vs previous update

Starts in period

3/5
Actual / baseline planned

Finishes in period

2/4
Actual / baseline planned

DCMA score

5/14
Checks passed

Contract adjustments · not in baseline

Early warnings & compensation events

CEs excludedEWs excluded

Completion Date

23 Sept 2025
CEs not applied

Forecast completion

18 Oct 2025
EWs not applied

Adjusted variance

+25.2d
same as baseline variance

CE cost confirmed

£48,500
£36,500 pending

Live EW exposure

£8,000
2 live · 15d

Data date 01 Apr 2025

Overall progress S-curve

  • Actual
  • Actual in month
  • Forecast
  • Planned (baseline)
  • Planned in month
2025-012025-032025-052025-072025-092025-110%25%50%75%100%0%5%10%15%20%Data date

Incomplete activities (days)

Total float distribution

< 001-1011-2021-44> 440481216

Baseline vs forecast

Key dates & milestones

IDMilestoneStatusBaselinePreviousForecastVar (d)Moved (d)TF
A1000Contract Starting DateComplete06 Jan 202506 Jan 202506 Jan 20250.00.0—
A1010Access Date - Site PossessionComplete20 Jan 202520 Jan 202520 Jan 20250.00.0—
A1900Sectional Completion - BridgeNot started30 Jun 202510 Jul 202514 Jul 2025+14.0+4.096.2
A1990Completion DateNot started23 Sept 202503 Oct 202518 Oct 2025+25.2+15.4-25.2

Lowest total float

Critical & near-critical

IDActivityStartFinishTF (d)
W1010Bulk Earthworks Cut01 Apr 202516 May 2025-25.2
W1030Carrier Drainage Installation16 May 202515 Jun 2025-25.2
W1050Filter Drains & Gullies15 Jun 202505 Jul 2025-25.2
P1000Sub-base & Capping Layer10 Jul 202509 Aug 2025-25.2
P1010Kerbs & Footways20 Jul 202514 Aug 2025-25.2
U1040Traffic Signals Installation14 Aug 202513 Sept 2025-25.2
C1000Signals Commissioning13 Sept 202523 Sept 2025-25.2
C1020Road Safety Audit Stage 323 Sept 202503 Oct 2025-25.2
C1030As-built Records & H&S File28 Sept 202518 Oct 2025-25.2
A1990Completion Date18 Oct 202518 Oct 2025-25.2
P1020Binder Course09 Aug 202524 Aug 2025-22.2
P1030Surface Course24 Aug 202503 Sept 2025-22.2
P1040Road Markings & Studs03 Sept 202510 Sept 2025-22.2
P1052Vehicle Restraint System27 Aug 202508 Sept 2025-10.2
P1051Permanent Signage27 Aug 202506 Sept 2025-8.2
U1020Street Lighting Ducting05 Jul 202525 Jul 2025-5.2
W1020Embankment Fill & Compaction11 Apr 202521 May 20250.25
U1030Street Lighting Columns & Cabling25 Jul 202519 Aug 20252.8
C1010Lighting Energisation19 Aug 202526 Aug 20252.8
D1030Technical Approval (AIP)12 Mar 202505 Apr 20254
S1000Piling - Abutments05 Apr 202525 Apr 20254
S1010Pile Caps, Abutments & Wingwalls25 Apr 202525 May 20254
S1020Precast Beam Installation25 May 202530 May 20254
S1030Bridge Deck Slab30 May 202529 Jun 20254
S1040Parapets & Waterproofing29 Jun 202514 Jul 20254